M-119 Lakeshore Dr. Electric Line Rebuild Phase 3
The City of Harbor Springs is accepting bids for Phase 3 of its M-119 Lakeshore Dr. Electric Line Rebuild project. Sealed bids will be accepted before 11:00 AM on Tuesday, December 21, 2021. Target project completion date is November 18, 2022. Please see the bid documents for more information.
M-119 Lakeshore Dr Rebuild Ph3 – Bid Documents
M-119 Lakeshore Dr Rebuild Phase 3 Dwgs 11-19-21
09 M-119 Lakeshore Dr Rebuild Ph3 Unit Lists
The overall scope of the project includes reconstruction of 6,750’ of three-phase 2.4/4.16kV overhead distribution line
with new three-phase #1/0 Hendrix aerial spacer cable construction along M-119 / Lakeshore Drive from Forest Beach
Road west to Ridge Road (approximately 1.3 miles in total length.) The distribution line will remain within the same
centerline along MDOT road ROW. Construction will be aerial spacer cable utilizing 052AWA messenger and #1/0 AL
phase conductor and includes a voltage conversion to 7.2/12.5kV. The project includes all necessary work to set new
poles, layout existing conductors, to install new conductor, to transfer existing taps, transformers, secondaries, and
service conductors, and to remove existing poles, conductor, and hardware. All necessary traffic control and signage to
meet MDOT requirements for work along this narrow section of M-119 is required. This project is being undertaken to
improve system reliability in a heavily treed area along a main three-phase circuit.
The Owner will furnish certain material as listed in the Project Manual to the Contractor. The Contractor will be
required to pickup and transport all material which is supplied from the Owner’s warehouse to the project site and also
be responsible for receipt and unloading of large material at the Project site(s).